what is acceptance testing and how is it significant to a information system
 

bazookie

Member
Joined
May 28, 2008
Messages
45
Gender
Male
HSC
2008
Acceptance testing is performed by the system users before the system goes operational. This is significant because it submits the information system to a realistic simulation of how it will be used when it does go operational. This means that most errors which might have been overlooked by the developers will be found and fixed before the system is implemented.
 

Makro

Porcupine
Joined
May 16, 2006
Messages
415
Location
In between.
Gender
Male
HSC
2009
bazookie said:
Acceptance testing is performed by the system users before the system goes operational. This is significant because it submits the information system to a realistic simulation of how it will be used when it does go operational. This means that most errors which might have been overlooked by the developers will be found and fixed before the system is implemented.
Spot on. My notes go on to mention that it's first tested with "test data" and then "live data" (actual data that the organisation would use) before it is implemented. Not that it's entirely relevant.
 

SamD

Member
Joined
Jul 21, 2002
Messages
256
Gender
Male
HSC
N/A
Acceptance testing is largely about the client accepting the final system (so that they will then pay the bill). As stated above, it would likely include a variety of different tests (volume, simulated, live, etc), however the aim of acceptance testing is to confirm that the original requirements have been met and hence the system is complete and functional. Often tests are constructed to specifically confirm that each requirement has been fulfilled. For instance, particular response times may have been a requirement - this is tested and if within sepcifications the requirement is accepted by the client as having been achieved. Each requirement is specifically tested and if all have been met then the client accepts the system as complete. For larger systems an outside testing organisation may perform the acceptance tests on behalf of the client and for smaller projects the client may perform the acceptance tests alongside the developers.

HTH